The Daily Item, Sunbury, PA

March 31, 2013

Chestnut Street reconstruction


For The Daily Item

MIFFLINBURG —

The $3.9 million project to reconstruct Route 45 (Chestnut Street) in Mifflinburg, from Route 104 to Forest Hill Road, will begin on March 25. at the intersection of Route 45 and Forest Hill Road will be reconstructed over one weekend, beginning Friday, April 5 at 8 p.m. and ending Monday, April 8 at 6 a.m.



The reconstruction phases of Route 45, from Eighth Street to Forest Hill Road, will begin April 8. That morning, the contractor will close down the first three block area from Eighth Street to Fifth Street and begin reconstruction. After this is completed, the crews will work their way east until they finish the reconstruction work. The reconstruction work on Route 45 will be done in three-block sections at a time.